CarbonNeeti

Free tool

CCTS target lookup and gap estimate

Find your plant in the notified CCTS target schedules, see its baseline and target GEI, and estimate whether it would be eligible to be issued or need to surrender carbon credit certificates. No sign-up.

Loading

How it works

  • The target GEI for each compliance year is the plant's row in the notified schedule: G.S.R. 739(E), and G.S.R. 25(E) with its refinery and textile tables as substituted by G.S.R. 794(E). The baseline year is FY 2023-24.
  • G.S.R. 517(E) for iron and steel is a draft. Its figures are shown as proposed and never used as a binding target.
  • GEI = GHG emissions on the CCTS boundary (tCO2e) / equivalent output in the year.
  • Gap = (target GEI - achieved GEI) x output. Above zero, the plant would be eligible to be issued that many certificates; below zero, it would need to surrender that many. 1 certificate = 1 tCO2e. CCTS uses IPCC AR5 global warming potentials.

The arithmetic is the same function CarbonNeeti uses for a plant's credit position, so the two round the same way (half up, to six decimals). The Scope 1 fuel calculator includes the fuel's CH4 and N2O, which CCTS does not count, so its figure is higher than the CCTS one for the same fuel.

The method step by step, with a worked example: read the guide.

Questions

What is GEI?

Greenhouse gas emission intensity: the tonnes of CO2e a plant emits for each unit of its equivalent output in a year. Under CCTS it counts CO2 and PFCs inside the plant boundary, plus the emissions of the electricity and heat it buys, minus what it exports. CH4, N2O, HFCs and SF6 stay in the GHG inventory but are not counted.

What happens if a plant misses its target?

It owes carbon credit certificates for the gap: the target GEI minus the achieved GEI, times the year's output, one certificate for each tonne of CO2e. A plant that beats its target can be issued certificates for the difference, after verification and the Bureau of Energy Efficiency's process.

Which plants are covered?

The plants named in the schedules of the Greenhouse Gases Emission Intensity Target Rules, 2025. G.S.R. 739(E) of 08/10/2025 notified aluminium, cement, chlor-alkali and pulp and paper plants. G.S.R. 25(E) of 13/01/2026 notified petrochemical, petroleum refinery and textile plants and more aluminium plants; G.S.R. 794(E) of 07/09/2026 substituted its refinery and textile tables. G.S.R. 517(E) of 26/06/2026 is a draft for iron and steel plants, open to objections, so its figures are not binding yet.